๐Ÿ• Recent Shifts โ€” quick switch
Date & Shift
2026-07-17
Day โ€” Team C
TOTAL NDT OK
339
Units
TOTAL HC&FC REJECT
25
Units
H&F REJECTION %
6.63%
of total production
NDT REJECTION %
3.45%
of total production
DOWNTIME (min)
120
min
๐Ÿ“‹
GENERAL INFORMATION
Date:
2026-07-17
Shift:
Day
Supervisor:
Al Julanda
Team:
C
Total Attendance:
16
Total Absent:
3
Was the Lean Meeting conducted?:
Yes
โš ๏ธ
SAFETY OBSERVATIONS
NoObservationStatus
โ€” No observations recorded โ€”
๐Ÿ”ฅ
FURNACE STATUS
Furnace Mass Received (Ton) Consumed (Ton) Metal Added (Ton) Mass End of Shift (Ton) Remarks
HA
min: 28T
19.40
โš  Below minimum
-0.10 0.00 19.50 โ€”
HC
min: 24T
21.10
โš  Below minimum
0.90 0.00 20.20 โ€”
SWM1 0.00 0.00 0.00 0.00 โ€”
SWM2 0.00 0.00 0.00 0.00 โ€”
๐ŸŒŠ
LAUNDER CONDITION
StageConditionComments
Received Good HA to SWM2 bad ( metal solidify)
Hand Over Good HA to SWM2 bad ( metal solidify)
๐Ÿญ
CASTING PRODUCTION
M/C No. Status Mold Type NDT OK HC & FC Reject NDT Reject Total Rejection % H&F Rej % NDT Rej % Remarks
6 Running 640-17 102 4 1 107 4.7% 3.7% 0.9% โ€”
7 Running Smx201-22 60 5 5 70 14.3% 7.1% 7.1% โ€”
14 Running R69-18 4 3 0 7 42.9% 42.9% 0.0% โ€”
14 Stopped R69-18 59 3 3 65 9.2% 4.6% 4.6% target over
15 Running cv98 32 4 0 36 11.1% 11.1% 0.0% โ€”
16 Running 666 82 6 4 92 10.9% 6.5% 4.4% โ€”
TOTAL PRODUCTION 377 โ€”โ€”โ€”โ€”
TOTAL REJECTION 38 10.1% 6.6% 3.4% โ€”
๐Ÿ”ง
MACHINE BREAKDOWN REPORT
M/CIssueDownTime (min)Action TakenPending ActionResponsibleStatusOdoo Notification
LDPC6 conveyor issue 0 min โ€” โ€” โ€” In Progress โ€”
deflashing 2 sensor issue 120 min โ€” โ€” โ€” Open โ€”
๐Ÿ› ๏ธ
DIE MAINTENANCE PLAN
Die ModelStatusRemarks
640-17 M1 Completed โ€”
smx201-22 M5 โ€” โ€”
LPDC17 In Progress โ€”
๐Ÿ“
ADDITIONAL REMARKS

rej wheels need to be added continuously to HA to run 5 mc

โœ๏ธ Start a New Report